(Bloomberg) -- The cost to build the Trans Mountain pipeline expansion has increased 70% to C$12.6 billion ($9.5 billion) because of legal delays to the project and accommodations made to indigenous communities along its route, the CBC reported.

The figure includes C$1.1 billion spent by the project’s previous owner, Kinder Morgan Inc., but excludes the C$4.5 billion Justin Trudeau’s government spent to purchase the pipeline, the CBC reported. Trans Mountain Chief Executive Officer Ian Anderson is expected to announce the cost increase during a news conference Friday, the CBC reported, citing people familiar with the matter.

The cost increase threatens to be a political liability for the Canadian prime minister, who has disappointed some in his environmentalist base over his support for the crude-oil conduit. Finance Minister Bill Morneau also has scheduled a press conference for this afternoon in Ottawa.

The project would boost daily shipping capacity by 590,000 barrels, to a total of 890,000 barrels, helping relieve a transport bottleneck that has weighed on Canada’s oil industry. The pipeline, which runs from Edmonton to a shipping terminal near Vancouver, also may help develop new markets for the country’s crude in Asia.

To contact the reporter on this story:
Kevin Orland in Calgary at korland@bloomberg.net

To contact the editors responsible for this story:
Simon Casey at scasey4@bloomberg.net
Stephen Wicary, Chris Fournier



WHAT DO YOU THINK?


Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.


Most Popular Articles