BP Continues to Develop Top Kill Ops

BP provideded an update on developments in the response to the MC252 oil well incident in the Gulf of Mexico.

Subsea Source Control and Containment

Subsea efforts continue to focus on progressing options to stop the flow of oil from the well through interventions via the blow out preventer (BOP) and to collect the flow of oil from the leak points. These efforts are being carried out in conjunction with governmental authorities and other industry experts.

Plans continue to develop a top kill operation where heavy drilling fluids are injected into the well to stem the flow of oil and gas and ultimately kill the well. Successfully killing the well may be followed by cement to seal the well. Most of the equipment is on site and preparations continue for this operation, with a view to deployment in a few days.

This is a complex operation requiring sophisticated diagnostic work and precise execution. As a result, it involves significant uncertainties and it is not possible to assure its success or to put a definite timescale on its deployment.

Drilling of the first relief well, which began on May 2 continues as does drilling of a second relief well, begun on May 16. Each of these wells is estimated to take some three months to complete from the commencement of drilling.

Work goes on to optimize the oil and gas collected from the damaged riser through the riser insertion tube tool (RITT). The collection rate continues to vary, primarily due to the flow parameters and physical characteristics within the riser.

In the period from May 17th to May 23rd, the daily oil rate collected by the RITT has ranged from 1,360 barrels of oil per day (b/d) to 3,000 b/d, and the daily gas rate has ranged from 4 million cubic feet per day (MMCFD) to 17 MMCFD.

In the same period, the average daily rate of oil and gas collected by the RITT containment system at the end of the leaking riser has been 2,010 barrels of oil per day (BOPD) and 10 MMCFD of gas. The oil is being stored and gas is being flared on the drillship Discoverer Enterprise, on the surface 5,000 feet above.
The RITT remains a new technology and both its continued operation and its effectiveness in capturing the oil and gas remain uncertain.

The US Government has appointed a flow rate technical team (FRTT) to determine the well flow rate. The FRTT includes the US Coast Guard, NOAA, MMS, Department of Energy and the US Geological Survey. BP will continue to promptly provide all information necessary to make as accurate an assessment as possible of the rate of flow.

Surface Spill Response and Containment

Work continues to collect and disperse oil that has reached the surface of the sea. Over 1,100 vessels are involved in the response effort, including skimmers, tugs, barges and recovery vessels.

Intensive operations to skim oil from the surface of the water have now recovered, in total, some 243,000 barrels (10.2 million gallons) of oily liquid. The total length of boom deployed as part of efforts to prevent oil reaching the coast is now nearly 2.5 million feet, including over 730,000 feet of sorbent boom.

In total, over 22,000 personnel from BP, other companies and government agencies are currently involved in the response to this incident. So far 23,000 claims have been filed and 9,000 have already been paid.

The cost of the response to date amounts to about $760 million, including the cost of the spill response, containment, relief well drilling, grants to the Gulf states, claims paid and federal costs. It is too early to quantify other potential costs and liabilities associated with the incident.


Most Popular Articles