Nov 27 (Reuters) - TransCanada Corp's existing Keystone pipeline has leaked substantially more oil, and more often, in the United States than indicated in risk assessments the company provided to regulators before the project began operating in 2010, according to documents reviewed by Reuters.
The Canadian company is now seeking to expand the pipeline system linking Alberta's oil fields to U.S. refineries with its proposed Keystone XL project, which has U.S. President Donald Trump's backing.
The existing 2,147-mile (3,455 km) Keystone system from Hardisty, Alberta, to the Texas coast has had three significant leaks in the United States since it began operating in 2010, including a 5,000-barrel spill this month in rural South Dakota, and two others, each about 400 barrels, in South Dakota in 2016 and North Dakota in 2011.
Before constructing the pipeline, TransCanada provided a spill risk assessment to regulators that estimated the chance of a leak of more than 50 barrels to be "not more than once every seven to 11 years over the entire length of the pipeline in the United States," according to its South Dakota operating permit.
For South Dakota alone, where the line has leaked twice, the estimate was for a "spill no more than once every 41 years."
The spill risk analysis was conducted by global risk management company DNV GL. A spokesman for DNV did not respond to a request for comment.
Members of South Dakota's Public Utilities Commission told Reuters last week they could revoke TransCanada's operating permit if an initial probe of last week's spill shows it violated the terms of the license.
Those terms include requirements for standards for construction, regular inspections of pipeline infrastructure, and other environmental safeguards.
"They testified that this is going to be a state-of-the-art pipeline," said one of the commissioners, Gary Hanson. "We want to know the pipeline is going to operate in a fashion that is safe and reliable. So far it's not going well."
TransCanada shut a section of the line while it cleans up the leak, which occurred near the town of Aberdeen on Nov. 16. An official did not respond to a request for comment.
The spill took place days before regulators in neighboring Nebraska approved a route for TransCanada's proposed Keystone XL pipeline through the state, lifting the last major regulatory hurdle for the expansion that has been delayed for years by environmental opposition.
Trump handed TransCanada a presidential permit for Keystone XL in March, reversing former President Barack Obama's decision to reject the line on economic and environmental grounds, saying that it would create jobs and boost national security.
TransCanada's spill analysis for Keystone XL, which would cross Montana, South Dakota and Nebraska, estimates 2.2 leaks per decade with half of those at volumes of 3 barrels or less. It estimated that spills exceeding 1,000 barrels would occur at a rate of once per century.
(Reporting by Valerie Volcovici and Richard Valdmanis)
WHAT DO YOU THINK?
Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.
- Weatherford CEO's Rebound Plan Relies On Getting Smaller
- Iran Says Oil Market Is Too Tight For US Zero Exports Target
- China's Squeezed 'Teapots' Eye Petchem Path To Riches
- Baker Hughes: US Drillers Add Oil Rigs For Second Week In Three
- Venezuela Hands China More Oil Presence, But No Mention Of New Funds
- Gunvor CEO Sees Russian Refining Capacity Taking Hit from Drone Strikes
- Sinopec Engineering Posts Higher Annual Petrochemicals Revenue
- Subsea7 Secures Contract to Service Woodside's Trion
- These Factors Helped Brent Oil Price Break Above $85
- Imperial Pipeline in Winnipeg Goes Offline for Three Months
- Adnoc Inks Supply Deal for Ruwais LNG Project with Germany's SEFE
- Gaz System to Acquire Gas Storage Poland
- Norway Regulator Blasts Proposal to Halt New Oil and Gas Permits
- Chinese Mega Company Makes Major Oilfield Discovery
- EIA Drops 2024 Henry Hub Gas Price Forecast
- EIA and Standard Chartered Offer Up Latest Oil Price Predictions
- Red Sea Region Sees Another Watershed Incident
- Chevron Oil Project in Kazakhstan to Cost $48.5B
- OPEC Voices Encouragement after IEA Affirms Support for Oil Security
- Biden Govt Bares Strategy for Freight Charging, Hydrogen Fueling Infra
- Rystad Looks at the Buzz Around White Hydrogen
- Ukraine Hits Third Russian Refinery In Escalating Drone Strikes
- VIDEO: Missile Attack Kills Crew Transiting Gulf of Aden
- Norway Regulator Blasts Proposal to Halt New Oil and Gas Permits
- Chinese Mega Company Makes Major Oilfield Discovery
- What Is the Biggest Risk to Offshore Oil and Gas Personnel in 2024?
- Is Peak Oil Demand Close?
- Vessel Sinks in Red Sea After Missile Strike
- JP Morgan, Standard Chartered Reveal Latest Oil Price Forecasts
- Exxon Rights in Stabroek Do Not Apply to Hess Merger with Chevron: Hess
- Rystad Forecasts Net Production of Top Permian Producers in 2024
- Analysts Reveal Latest Oil Price Outlook Following OPEC+ Cut Extension