TransCanada, ConocoPhillips To Expand Keystone To Gulf Coast
Plans to expand to the U.S. Gulf Coast follow successful negotiations with several prospective shippers who have agreed, subject to regulatory approvals, to make shipping commitments of approximately 300,000 barrels per day to the U.S. Gulf Coast for an average term of 18 years during a binding open season which begins today. In addition, prospective shippers have also agreed to commit another 35,000 barrels per day to Wood River and Patoka, Illinois during a future open season expected in the third or fourth quarter of 2008. With these commitments Keystone has now secured long-term commitments for approximately 830,000 barrels per day for an average term of 18 years. These commitments represent approximately 75 percent of the commercial design of the system.
"The Keystone expansion will be the first direct pipeline to connect a growing and reliable supply of Canadian crude oil with the largest refining market in North America," says Hal Kvisle, TransCanada president and chief executive officer. "The Keystone Pipeline will be constructed and operated as an integrated system with delivery points in the U.S. Midwest and U.S. Gulf Coast."
The Keystone expansion includes an approximate 3,200-kilometer (1,980-mile), 36-inch crude oil pipeline starting at Hardisty, Alberta and extending south to a delivery point near existing terminals in Port Arthur, Texas and, subject to shipper support, will include an additional approximate 80-kilometer (50-mile) pipeline lateral to the Houston, Texas area. With the addition of incremental pumping facilities, the Keystone Pipeline system could be further expanded from 1.1 million barrels per day to 1.5 million barrels per day.
During the binding open season Keystone will seek additional shipping commitments from interested parties. Once Keystone completes the open season process it will proceed expeditiously with the necessary regulatory applications in Canada and the U.S. for approvals to construct and operate the proposed facilities. Construction of the facilities is anticipated to commence in 2010 following the receipt of the necessary regulatory approvals. As a result, the majority of the US$7.0 billion in additional capital investment required to expand Keystone to the U.S. Gulf Coast is expected to be made between 2010 and 2012.
Certain parties who have agreed to make volume commitments to the Keystone expansion have an option to acquire up to a combined 15 percent equity ownership in the Keystone partnerships.
TransCanada is responsible for developing, constructing and operating the Keystone pipeline and has initiated outreach activities with key stakeholders including local communities and landowners along the expansion route. It is expected that deliveries to Wood River and Patoka, Illinois will commence in late 2009. Deliveries to Cushing, Oklahoma are expected to commence in late 2010 and deliveries to the U.S. Gulf Coast are expected to begin in 2012.
During the binding open season period, which expires at noon (Mountain Time) on September 4, 2008, TransCanada, on behalf of Keystone, will accept binding bids from parties for firm transportation capacity for transportation of crude oil from Hardisty, Alberta to Port Arthur or Houston, Texas. Interested parties are invited to contact Marty Heeg at 403.920.2101 or David Diakow at 403.920.6019 for more information. The Keystone expansion project web page (www.transcanada.com/keystone/kxl.html) provides additional information about the project including a summary of the open season documents and a map of the proposed pipeline corridor.
With more than 50 years' experience, TransCanada is a leader in the responsible development and reliable operation of North American energy infrastructure including natural gas pipelines, power generation, gas storage facilities, and projects related to oil pipelines and LNG facilities. TransCanada's network of wholly owned pipelines extends more than 59,000 kilometers (36,500 miles), tapping into virtually all major gas supply basins in North America. TransCanada is one of the continent's largest providers of gas storage and related services with approximately 355 billion cubic feet of storage capacity. A growing independent power producer, TransCanada owns, controls or is developing approximately 8,300 megawatts of power generation.
- Governor Issues Disaster Declaration for Southeast Texas
- Exxon Building Largest Renewable Diesel Plant In Canada
- EU Considers Capping Russian Fuel Prices at $100
- World Still Waiting to See What China Reopening Means
- Gasoline Price More Expensive Than Year Ago Levels
- Former Brazilian Senator Takes Over Petrobras Helm
- Oil Traders Weigh Up Market This Week
- RWE-National Grid JV Submits Bid For New York State Wind Rights
- Petrobras Completes $1.6B Sale Of Albacora Leste Field To Petro Rio
- BSEE Checks Out Coastal Virginia Offshore Wind Project Progress
- Valaris Employee Reported Missing from Rig
- Is The USA Strategic Petroleum Reserve Stock Dangerously Low?
- How Will Russia's Oil and Gas Industry Fare in 2023?
- Oil and Gas Security Trends in 2023
- Fundamentals Strong Enough for $90+ Oil Period
- USA Drops Rigs
- Texas Oil & Gas Industry Paid Record $24.7Bn In Taxes And Royalties
- Risk Premium Embedded in USA NatGas Vanishes
- Texas O&G Sector Closes 2022 With Continued Employment Growth
- Police to Board Valaris Rig After Worker Reported Missing
- Egypt Makes 53 New Oil And Gas Discoveries In 2022
- Valaris Employee Reported Missing from Rig
- Texas Governor Calls For Atmos Energy Investigation
- Search For Four Missing In GoM Chopper Crash Suspended
- Louisiana, Texas To Gain Thousands of Energy Jobs At Start of 2023
- Where Will WTI Oil Price Be at End 2023?
- Is the USA Shale Boom Over?
- Talos Makes Two Commercial Discoveries In Gulf Of Mexico
- Gasoline and Diesel Prices Expected to Fall
- Iran Oil Gushes Into Global Market