Australia's Triple Energy Ltd. provided Tuesday the following update on the drilling activities on the Company's Aolong Joint Venture project in Heilongjiang province, China.

Niaoshan-1 Well

As of 10:00 am Sept. 28 the Niaoshan-1 well had reached its programmed total depth of 4,137 feet (1,261 meters) measured depth. Upon conclusion of wireline operations a decision will be made on the next steps with regard to well completion.

Yixin-1 Well

The Yixin-1 well remains at 121 feet (37 meters) measured depth pending the arrival of necessary additional equipment as previously advised. The necessary equipment has now been mobilized to site.