JKX provided a status update of the redevelopment of the Koshekhablskoye field in southern Russia.
Gas Processing Facility & First Gas
Fabrication of the key components of the GPF plant in Sharjah was completed during the last quarter of 2010 with the final shipment leaving port at the end of December, slightly ahead of schedule. All equipment has now been off-loaded and cleared through customs in the Russian port of Novorossiysk, some 300km from the field. Trucking to site commenced in early January, with final deliveries scheduled for the end of this week. Foundations for the equipment are in place and the construction teams have begun installation. Installation and construction of locally sourced equipment and buildings is nearing completion with hook-up and commissioning of the plant scheduled to commence by the end of the first quarter. First commercial gas production remains on target for mid-year.
Flowlines and Export Lines
Installation and testing of all flowlines, together with control and injection lines, has been completed. The twin export lines have been installed tested and tied-in to the Gazprom trunk line and are awaiting connection to the manifolds at the GPF.
Well Recompletions
Development Wells 20 and 27 have been successfully completed and tested in the Oxfordian limestone reservoir and are suspended ready for production. Together they have a potential delivery capacity of 30 MMcfd.
Development Well 25 on the north flank of the field has been re-entered using the Geostream KES-536 rig, and the remainder of the tubing recovered. Drilling of the 260m sidetrack into the limestone reservoir will kick-off this week at 5,490m with a targeted TD of 5,700m. Completion and testing of Well 25 is scheduled for the end of the first quarter.
Development Well 15, deep on the east flank of the field, was sidetracked to a depth of 5,755m with strong gas shows and encouraging logs. Disappointingly, the sidetracked well bore did not stay open during testing with an obstruction preventing deployment of the coiled tubing to TD in the open hole section. Due to the priority given to the other wells in the remainder of the first phase, remedial action, which may include a new sidetrack, would be undertaken as part of the second phase of well recompletions later in 2012.
Tubing has now been recovered from the Callovian appraisal Well 09 to a depth of 5,312m using the Kremco-900 rig. Preparations are currently underway to sidetrack the well through the Callovian sandstone reservoirs to a TD of 5,500m. Completion and testing of Well 09 is now scheduled for the second quarter of the year.
A smaller A-125 rig has been used to prepare exploration Well 22 for deepening. The well has been suspended at 4,885m awaiting mobilization of the Geostream KES-536 rig to deepen the well to the Callovian sandstone reservoirs with a TD of 5,570m. Completion and testing of Well 22 is scheduled for the third quarter of the year.
JKX Chief Executive, Dr Paul Davies, said, "We are very pleased with the progress made on the Koshekhablskoye field in Russia, which is on track to commence gas production by the end of 1H at the plant design capacity of 40 MMcfd. This keeps us on track to achieve the Group's overall near term production objective of 20,000 boepd."
- What Would War-End Mean for Global Oil and Gas?
- BP Boss Talks Energy Trilemma
- Fitch Solutions Reveals Latest Oil Price Forecast
- EU Playing Catch-Up To Secure Sustainable Energy
- US Microgrid Market Developing Rapidly With 10GW Capacity
- Algeria Hopes Energy Deal With Chevron Is Concluded This Year
- Attacks Highlight Continued Vulnerability of Ukraine Ports
- Denmark Awards First Three Offshore CO2 Storage Licenses
- Aker Solutions Signs Deal For Electrification Of Draugen Platform
- Oil Rises as Saudi Issues Price Hike to Asia
- New SPR Bill Passes House
- Shell CEO Says World 'Desperately In Need' Of Natural Gas
- Energy Services Sector Will Grow To $1 trillion In 2025
- Fate Of $8Bn Alaska Oil Project To Be Resolved In Next 30 Days
- Winter Storm Mara Update
- Gov't Tampering Puts Australian Gas Market In Unenviable Position
- What Would War-End Mean for Global Oil and Gas?
- OPEC+ Exports Show Russia Surges While Saudi Arabia Dials Back
- Fed Will Be One Of The Leading Oil Price Drivers in 2023
- Will A New Iran Nuclear Deal Be Agreed to in 2023?
- Valaris Employee Reported Missing from Rig
- Gasoline and Diesel Prices Expected to Fall
- New SPR Bill Passes House
- Is the USA Shale Boom Over?
- Higher Oil Prices Have Not Led to More Exploration
- Shell Finds Gas In Pensacola High-Impact Well Off UK
- Iran Oil Gushes Into Global Market
- Will Oil Hit $100 Per Barrel in 2023?
- What Bad Habits Should Oil and Gas Jobseekers Avoid?
- Eni, Chevron Make Significant Gas Discovery Off Egypt