I. Core responsibilities — Refinery Project Supervisor
- I.1 — Field execution leadership: Direct day-to-day construction and installation activities in operating and greenfield refinery units, ensuring scope, quality, and HSE compliance.
- I.2 — Workface planning: Build and run 2–4 week look-aheads, constraint removal, and Installation Work Packages (IWPs) for piping, mechanical, civil, E&I, and insulation/scaffolding/painting (ISP) crews.
- I.3 — SIMOPS and permit control: Coordinate simultaneous operations, lockout/tagout, and Permit-to-Work (hot/cold work, confined space, energization) with Operations.
- I.4 — Constructability & tie-ins: Validate field routing, access, lifting, and tie-in windows; manage hot taps, blinds, spades, and weld sequencing in live units.
- I.5 — Progress and productivity tracking: Verify earned quantities, man-hours, and S-curve updates; challenge contractor reports with field measurement.
- I.6 — Quality verification: Enforce ITPs, weld maps, NDT hold points, hydro/pneumatic test packs, torque/tension control, and flange management.
- I.7 — Change and risk control: Administer Management of Change (MoC), RFIs, NCRs, and risk registers; implement mitigations and contingency drawdowns.
- I.8 — HSE stewardship: Lead toolbox talks, JSAs, hazard hunts; verify barriers (gas testing, barricading, ATEX compliance), and stop-work authority.
- I.9 — Contractor oversight: Supervise contractor supervisors/foremen; balance craft loading, shift patterns, and ensure adherence to method statements.
- I.10 — Materials and logistics: Expedite critical spools, valves, catalysts, refractory, and long-leads; manage laydown, preservation, and receiving QC.
- I.11 — Lifting and rigging control: Approve lift plans (ordinary/critical), crane schedules, exclusion zones, and rigging inspections.
- I.12 — Turnaround readiness and execution (if TAR/STO): Own event sequence, critical path discipline, discovery work screening, and daily de-bottlenecking.
- I.13 — Pre-commissioning and handover: Oversee flushing, leak tests, reinstatement, loop checks, and turnover dossier completion to commissioning/operations.
- I.14 — Reporting and governance: Issue daily/weekly status, look-aheads, KPIs (CPI, SPI, TRIR), and risk/opportunities to the Project Manager.
- I.15 — Lessons learned and closeout: Capture execution learnings, as-built redlines, and final quantities for benchmarking and future estimates.
II. Required technical skills, soft skills, and physical demands
II.A — Technical skills
- II.1 — Refinery unit familiarity: CDU/VDU, FCC, hydrocracker, hydrotreaters, reformer, SRU/TGTU, tanks, utilities/OSBL.
- II.2 — Discipline breadth: Piping (ASME B31.3), pressure equipment (API 510/570 fundamentals), structural steel, civil, E&I, analyzers, refractory (API 936 basics).
- II.3 — QA/QC & testing: WPS/PQR/WPQ review, weld/NDT acceptance, hydro/pneumatic testing, electrical pre-energization checks, torque/tension verifications.
- II.4 — Workface planning & IWP/IWPs: Quantity take-off, constraint logs, tool/equipment readiness, and craft sequencing.
- II.5 — Project controls literacy: Earned value interpretation, schedule logic/float, trend and change control, accruals.
- II.6 — HSE & process safety: PTW, LOTO, confined space, hot work, SIMOPS, energy isolation, and basic understanding of HAZOP/LOPA actions.
- II.7 — Lifting & rigging: Lift categorization, crane charts, center-of-gravity and rigging plan verification.
- II.8 — Codes & standards (working knowledge): ASME, API, AWS D1.1, NFPA, IEC/NEC, NACE, OSHA/ISO.
II.B — Soft skills
- II.9 — Field leadership: Direct, decisive, and fair supervision of multi-craft crews under schedule pressure.
- II.10 — Communication: Crisp shift handovers, conflict resolution, contractor performance coaching, escalation discipline.
- II.11 — Decision-making: Rapid risk-based calls on rework, reroutes, temporary repairs, and tie-in readiness.
- II.12 — Planning mindset: Relentless look-ahead, constraint busting, and critical path thinking.
II.C — Physical demands
- II.13 — Field presence: 70–90% in plant; climbing ladders/scaffolds, working at heights and in confined spaces.
- II.14 — Conditions: Heat/cold, noise, fumes, and PPE; frequent night/weekend shifts during tie-ins and turnarounds.
- II.15 — Manual requirements: Walk long distances in large complexes; handle tools/equipment up to light-moderate loads safely.
II.D — Key control formulas (execution and controls)
- II.16 — Earned Value: \(EV=\sum \text{Budgeted Cost of Work Performed (BCWP)}\), \(PV=\sum \text{Budgeted Cost of Work Scheduled (BCWS)}\), \(AC=\sum \text{Actual Cost}\).
- II.17 — Performance indices: \(CPI=\frac{EV}{AC}\), \(SPI=\frac{EV}{PV}\). Forecasts: \(EAC=\frac{BAC}{CPI}\) or \(EAC=AC+\frac{BAC-EV}{CPI}\); \(ETC=EAC-AC\).
- II.18 — Percent complete (quantity-based): \(\%\text{Complete}=\frac{\text{Installed Quantity}}{\text{Total Quantity}}\times 100\%\).
- II.19 — Productivity factor: \(\text{PF}=\frac{\text{Earned Man-hours}}{\text{Actual Man-hours}}\).
- II.20 — Weld repair rate: \(\text{WRR}=\frac{\text{Repaired Welds}}{\text{Total Welds}}\times 100\%\).
- II.21 — Cost accrual estimate: \(\text{Accrual}=\%\text{Complete}\times \text{Committed Value}\).
III. Typical tools, software, and equipment used
- III.1 — Planning & controls: Primavera P6, MS Project, Excel/Power BI dashboards for S-curves, Earned Value tracking.
- III.2 — Document & model management: Aconex/Procore, Hexagon SmartPlant Foundation, AutoCAD, Navisworks; P&IDs, isometrics, 3D model markups.
- III.3 — Completions & turnover: PCS/WinPCS/Continuum-QEDI or similar completions systems; test pack and punchlist trackers.
- III.4 — CMMS & ERP: SAP PM/MM or Maximo for notifications, work orders, materials, and accruals.
- III.5 — HSE & permits: Digital PTW systems, gas detectors, intrinsically safe tablets/radios, access control systems.
- III.6 — Quality & inspection: Flange management tools, torque/tension devices, weld map/NDT reporting apps, PMI/UT coordination.
- III.7 — Lifting & rigging: Lift planning software/spreadsheets, crane load charts, taglines and certified rigging sets oversight.
Toolchain Snapshot: Primavera P6, Excel/Power BI, SAP PM/MM or Maximo, Aconex/Procore, SmartPlant Foundation, AutoCAD/Navisworks, digital PTW, completions database (PCS/QEDI), flange management and torque/tension toolsets, gas detection and ATEX-rated comms.
IV. Work environment
- IV.1 — Location: Onshore refinery (process units, tank farms, OSBL/ISBL), occasionally vendor shops and fabrication yards.
- IV.2 — Shifts/rotation: Projects: standard 5–2 with site walks; Turnarounds: 10–12 hour shifts, day/night; critical tie-ins on nights/weekends.
- IV.3 — Travel: Periodic trips to suppliers, offsite fabrication, and regulatory inspections.
- IV.4 — Exposure: Hydrocarbon processing areas, SIMOPS with live equipment, strict access and gas testing protocols.
V. Reporting lines and cross-functional interfaces
- V.1 — Reports to: Project Manager (capital projects) or Turnaround Manager (events); dotted-line to Construction Manager for large programs.
- V.2 — Direct reports: Field engineers, area coordinators; oversees contractor supervisors/foremen across disciplines.
- V.3 — Key interfaces: Operations, Maintenance, Inspection/Integrity (RBI), Process Engineering, I&E, HSE, QA/QC, Supply Chain/Materials, Project Controls, Document Control, Commissioning/Start-up, and external contractors/subcontractors.
Deliverables & Interfaces: Delivers field execution plans, 2–4 week look-aheads, daily/weekly reports, S-curves/KPIs, ITPs/NCRs, RFIs/MoCs, lift plans, test packs, redlines/as-builts, punchlists, and turnover dossiers to the Project Manager, QA/QC, Project Controls, and Commissioning; hands over reinstated systems to Operations for start-up.
VI. Career ladder and progression
- VI.1 — Next-step roles: Senior Refinery Project Supervisor ? Construction Superintendent / Area Construction Lead ? Turnaround Superintendent ? Project Manager (refinery) ? Turnaround/Capital Projects Manager.
- VI.2 — What’s needed to move up: Successful delivery of multi-discipline scopes (ISBL/OSBL), strong CPI/SPI performance, incident-free execution, demonstrated contractor performance management, and ownership of critical-path tie-ins.
- VI.3 — Development enablers: PMP or equivalent, AACE cost/schedule credentials, advanced PTW/SIMOPS leadership, lifting operations competence, and deeper API/ASME code fluency.
Progression Trigger: Typically promoted after 3–5 capital projects or 2–3 major turnarounds delivered with CPI = 0.95 and SPI = 0.95 over 24–36 months, plus a project management certification (e.g., PMP) and positive leadership evaluations.


Collaborate and learn alongside you peers. Professional development on your schedule. API training programs will help you advance your career. Browse our list of courses today.