AED reported that 7" casing has now been run to 2867m MDRT at the Lempuyang-1 exploration well in Block L, Brunei. The running of casing was delayed as a result of issues with drilling fluid losses arising from the increase in pressure and gas influx, as previously reported. Cementing of the shoe has now been completed resolving the drilling fluid loss.

The next steps will include the completion of the casing installation, testing of the BOP, drilling out the shoe and associated testing. Drilling in 6" hole is expected early next week.