US Officials Delay Well Testing

Deepwater Horizon Gulf of Mexico Oil Spill

Following a meeting with Secretary Chu and his team of scientific and industry experts, the National Incident Commander announced that additional analysis of the well testing procedure should be performed before starting the well integrity test. This analysis will be conducted at night and into the morning of July 14. Consequently, the well integrity test did not start July 13.

During this period, BP will continue to ramp up containment operations on the Helix Producer as well as continue to optimise the Q4000 operations. The Helix Producer has the capacity to capture approximately 20,000 – 25,000 barrels of oil per day. Historically, the Q4000 has flared an average of approximately 8,000 barrels of oil per day.

The sealing cap system, the Q4000 system, the flexible riser system, and the planned additional containment systems never before have been deployed at these depths or under these conditions, and their efficiency and ability to contain or flare the oil and gas cannot be assured.

Operations continue on the first relief well. Operations on the second relief well have been temporarily suspended at 15,963 feet to ensure that there is no interference with the first relief well. The relief wells remain the sole means to permanently seal and isolate the well.

More info on the Deepwater Horizon Gulf of Mexico Oil Spill

Events  SUBSCRIBE TO OUR NEWSLETTER

Our Privacy Pledge
SUBSCRIBE

Deepwater Horizon Images
Macondo Oil Leak Booms to Protect Breton NWR Shoreline Discoverer Enterprise Macondo BOP Oil Leak
Crewmen aboard the motor vessel Crewmen guide a cofferdam onto the deck Diagram & Photos of Horizon Riser / Pipe Deepwater Horizon in Flames (Apr 20)
71 more images view image library


From the Career Center
Jobs that may interest you
Petroleum Engineering Intern
Expertise: Petroleum Engineering|Student / Recent Grad
Location: Houston, TX
 
United States Rock Springs: Field Service Quality Coordinator - Cementing
Expertise: Operations Management|Planner / Scheduler|Production Engineering
Location: Rock Springs, WY
 
United States Duncan: Production Enhancement Technical Instructor
Expertise: HR - Trainer / Instructor|Production Engineering|Technical Manager
Location: Duncan, OK
 
search for more jobs

Brent Crude Oil : $52.96/BBL 1.03%
Light Crude Oil : $50.35/BBL 1.69%
Natural Gas : $3.19/MMBtu 0.63%
Updated in last 24 hours