Capping Stack Installed on MC252 Well

Deepwater Horizon Gulf of Mexico Oil Spill

The three ram capping stack was installed on the Deep Water Horizon LMRP at 7 p.m. CDT on July 12. The stack completes the installation of the new sealing cap.

Following installation of the capping stack and in line with the procedure approved by the National Incident Commander and Unified Area Command, the well integrity test will begin July 13 on the MC252 well.

For the duration of the test, which will be a minimum of 6 hours and could extend up to 48 hours, the three ram capping stack will be closed and all sub-sea containment systems (namely, the Q4000 and Helix Producer) will be temporarily suspended, effectively shutting in the well. It is expected, although cannot be assured, that no oil will be released to the ocean for the duration of the test. This will not however be an indication that flow from the wellbore has been permanently stopped.

Information gathered during the test will be reviewed with the relevant government agencies including the federal science team to determine the way forward. Options include reinstatement of containment as well as extending the test duration beyond 48 hours.

The sealing cap system never before has been deployed at these depths or under these conditions, and its efficiency and ability to contain the oil and gas cannot be assured.

The Helix Producer containment system started operations on July 12. The Q4000 containment system continues to capture oil and gas from the MC252 well and flare the hydrocarbons safely at the surface.

Relief well operations continue throughout this period and remain the sole means to permanently seal and isolate the well.

More info on the Deepwater Horizon Gulf of Mexico Oil Spill

Events  SUBSCRIBE TO OUR NEWSLETTER

Our Privacy Pledge
SUBSCRIBE

Deepwater Horizon Images
Smoke from Deepwater Horizon (Apr 21) Booms to Protect Breton NWR Shoreline Macondo Oil Slick (May 4) Deepwater Horizon Sinking (Apr 22)
Smoke Rising from Horizon (Apr 22) Workers Prep Booms to Protect Shoreline Cutting Macondo Riser ROV Accessing Horizon BOP Panel
71 more images view image library


From the Career Center
Jobs that may interest you
United States Odessa: Field Engineer - Logging and Perforating
Expertise: Field Development
Location: Odessa, TX
 
Project Procurement & Contracts Advisor (Subsea Equipment)
Expertise: Contracts Engineer|Purchasing|Subsea Engineering
Location: Houston, TX
 
Drilling Engineer II Job
Expertise: Drilling Engineering|Petroleum Engineering
Location: Houston, TX
 
search for more jobs

Brent Crude Oil : $53.92/BBL 2.79%
Light Crude Oil : $51.08/BBL 2.66%
Natural Gas : $3.3/MMBtu 3.22%
Updated in last 24 hours