Aker Barents commenced drilling operations for Det norske on well 25/1-11 Storklakken in PL 460 on December 31, 2009.

The aim of these operations is to discover oil that can be tied back to a future installation on the Frøy field, and thus improve Frøy project economics.

The Aker Barents semisub has now completed the top section of the well and will go to shore to assemble six hydraulic cylinders. According to the rig contract, Det norske will not pay rig dayrates during this repair.

As a result of the yard-stay, Det norske expects that the Storklakken well will be completed in mid-March, compared to early February.

 


RELATED COMPANIES
For More Information on the Offshore Rig Fleet:
RigLogix can provide the information that you need about the offshore rig fleet, whether you need utilization and industry trends or detailed reports on future rig contracts. Subscribing to RigLogix will allow you to access dozens of prebuilt reports and build your own custom reports using hundreds of available data columns. For more information about a RigLogix subscription, visit www.riglogix.com.