Xtract's Turkish Subsidiary Spins Bit at Sarikiz-3 Prospect

Xtract has provided an update on operations in the Alasehir license area at its Turkish associate company Extrem Energy AS ("Extrem").

Sarikiz-3 Drilling

Following completion of the concrete base, mobilization of the drilling rig commenced on December 28, 2009. The well was spudded yesterday, January 10, 2010. This was a few days later than hoped due to poor weather conditions during the mobilization phase.

The Sarikiz-3 prospect is located 525m to the northeast of Sarikiz-2 well at the junction of two intersecting 2D seismic lines. The proposed total depth is 1950m. The targeted Alasehir sandstones are expected to be encountered at depths between 1570m and 1850m. Depending upon hydrocarbon shows and the results of wire line log analysis, 7 inch casing will be run from the surface to below the target zones and cased-hole production testing will be carried out. The well cost is estimated to be approximately US$3.5m and the drilling program is planned on the basis of 45 rig days.

Based on a 2 square km area and an assumed net productive pay thickness of 20m, Extrem Energy's preliminary pre-drill P50 estimate of the recoverable oil in place from the Sarikiz-3 well is 5.75mbbl, based on an assumed 20% recovery factor.

Extrem holds 80% of the relevant license. Xtract holds 34% of Extrem.

Sarikiz-2 Production

Some unexpected delay was encountered in December due to late receipt of the well-site heating system from the manufacturer. The system has now been installed and tested and production is expected to commence this week based on natural flow.

Early production will be received by the refinery at Izmir using temporary delivery arrangements agreed with them. A contract has recently been agreed which provides for the refinery operator to build the necessary infrastructure there to receive larger volumes as the Sarikiz field is progressively brought on stream. Extrem will cover the investment costs associated with building the necessary infrastructure from sales of crude oil.

Information on the actual natural flow rate achieved and revised projected pumped rate will be supplied once flow has been stabilized. It is now expected that full pumped volumes from Sarikiz-2 will be produced and delivered by the end of Q1 2010. Until then, production is expected to be based on natural flow.

Alasehir/Sarikiz Field Development

In view of the high level of uncertainty over the possible extent of the oil-bearing structures in the wider Alasehir license area and in order to enhance planning of further wells, Extrem has been considering a project to undertake 3D seismic over the license area. The board has decided that the project should not commence immediately but should be assessed again based on the early production from Sarikiz-2 and the drilling results at Sarikiz-3. The 3D seismic project could therefore be conducted in the second half of 2010.



Our Privacy Pledge

Most Popular Articles

From the Career Center
Jobs that may interest you
Production Engineer
Expertise: Production Engineering
Location: Houston, TX
Senior Sales Representative - Oil and Gas
Expertise: Corrosion Engineering|Petroleum Engineering|Sales
Location: Harvey, LA
Gas Storage Reservoir Engineer
Expertise: Petroleum Engineering
Location: Houston, TX
search for more jobs

Brent Crude Oil : $50.79/BBL 1.30%
Light Crude Oil : $49.96/BBL 1.10%
Natural Gas : $2.77/MMBtu 2.12%
Updated in last 24 hours