VOG Drills Ahead at Logbaba Project in Cameroon

Victoria Oil & Gas has reported on its Logbaba gas and condensate project in Douala, Cameroon.

At Well La-105, following sidetracking of the 12-¼ inch hole section, 9-5/8 inch casing has been set to a depth of 5,965 feet measured depth and drilling has reached a depth of 6,330 feet measured depth. A top-drive and third mud pump have been fitted to the rig to increase drilling efficiency and the equipment for mud-cooling is being constructed on-site. Total depth of 10,300 feet is expected to be reached before the end of the year.

With the casing set above the 90 feet of gross pay previously intersected and announced on November 16, 2009, this pay zone will now be included behind the final 7 inch liner to allow for easier eventual production. Wireline logging has also been completed on the 12-¼ inch hole section.

The GeoDynamics Research passive seismic spectroscopy survey has been completed and a total of 74 measurements were taken. The data is now being processed and results are expected in around two months.

Related Companies

Our Privacy Pledge

Most Popular Articles

From the Career Center
Jobs that may interest you
Well Monitoring Specialist
Expertise: WellSite Supervisor
Location: Houston, TX
Chief Mechanic (6th Gen Drillship)(Contract)
Expertise: Rig Mechanic
Location: Houma, LA
ET (Deepwater Drillship)
Expertise: Rig Electrician
Location: Houma, LA
search for more jobs

Brent Crude Oil : $51.46/BBL 0.61%
Light Crude Oil : $50.52/BBL 0.64%
Natural Gas : $2.83/MMBtu 5.35%
Updated in last 24 hours