Maurel & Prom Starts Production from Onal in Gabon

Maurel & Prom reported that production at the Onal field began on March 9, 2009 with the opening of the first 11 wells on platforms PF-500, PF-700 and PF-900, at an initial provisional rate of 10,000 barrels per day at 100%.

Oil processing and storage commenced at the Onal facilities on February 23, following the start-up of the Omko field (production of 3,000 bbl/d at 100%).

The export pipeline (120 km) between Onal and the Coucal delivery point is currently being filled. The first oil is expected to arrive at Coucal before the end of the week.
 

Events  SUBSCRIBE TO OUR NEWSLETTER

Our Privacy Pledge
SUBSCRIBE


Most Popular Articles


From the Career Center
Jobs that may interest you
Construction Foreman - Midstream Construction
Expertise: Production Operator
Location: Kermit, TX
 
E&I Construction Foreman - Midstream Construction
Expertise: Production Operator
Location: Kermit, TX
 
Coil Tubing Pump Operator
Expertise: Fracturing
Location: San Antonio, TX
 
search for more jobs

Brent Crude Oil : $50.64/BBL 0.62%
Light Crude Oil : $48.04/BBL 1.47%
Natural Gas : $3.01/MMBtu 2.58%
Updated in last 24 hours