StatoilHydro has been granted consent to use the semisub Bideford Dolphin for production drilling of two wells on Oseberg Sor.

The consent applies to the drilling of wells 30/9-J-15H/AH and 30/9-J-13AH (oil producers) on the Oseberg Sor J structure.

According to the consent application, start-up is scheduled for January 1, 2009 and estimated duration of the drilling activity is 160 days.

The Bideford Dolphin is a semisubmersible Aker H-3 drilling facility built in 1975 and operated by Dolphin AS.
 


RELATED COMPANIES
For More Information on the Offshore Rig Fleet:
RigLogix can provide the information that you need about the offshore rig fleet, whether you need utilization and industry trends or detailed reports on future rig contracts. Subscribing to RigLogix will allow you to access dozens of prebuilt reports and build your own custom reports using hundreds of available data columns. For more information about a RigLogix subscription, visit www.riglogix.com.