StatoilHydro has received consent to conduct exploration drilling using the semisub Borgland Dolphin on the Visund field.

The consent applies to drilling of well 34/8-14A and S. The well belongs to Production License 120.

Borgland Dolphin, which is operated by Dolphin AS, is an Aker H3 facility built in 1976.

According to the application for consent, drilling is planned around August 15, 2008. The activity has an estimated duration of 119 days.

For More Information on the Offshore Rig Fleet:
RigLogix can provide the information that you need about the offshore rig fleet, whether you need utilization and industry trends or detailed reports on future rig contracts. Subscribing to RigLogix will allow you to access dozens of prebuilt reports and build your own custom reports using hundreds of available data columns. For more information about a RigLogix subscription, visit

Our Privacy Pledge

Most Popular Articles

From the Career Center
Jobs that may interest you
Well Monitoring Specialist
Expertise: WellSite Supervisor
Location: Houston, TX
Chief Mechanic (6th Gen Drillship)(Contract)
Expertise: Rig Mechanic
Location: Houma, LA
ET (Deepwater Drillship)
Expertise: Rig Electrician
Location: Houma, LA
search for more jobs

Brent Crude Oil : $49.98/BBL 1.59%
Light Crude Oil : $49.18/BBL 1.56%
Natural Gas : $2.73/MMBtu 1.44%
Updated in last 24 hours