Drews Landing Processing Facilities Up in 2008

The Rocksource Group is pleased to confirm that progress for installation of new processing facilities in the Drews Landing field in the U.S. is going according to plan.

The necessary work to connect to the gas export line is now under way, as is the final installation of the processing equipment, which will be followed by connecting and testing the entire facility.

The producing wells will be sequentially shut-in and then tied in to the new facilities and gradually opened up for production through the new facilities. After the high-pressure wells are tied-in and opened, compressors will be installed to increased production from wells with low-pressure zones in early 2008.