Seajacks Cuts Steel on Second Liftboat

Lamprell Energy cut first steel on December 6, 2007 in their Jebel Ali, Dubai fabrication yard for the hull of Seajacks' second harsh environment Liftboat. This is 5 weeks ahead of the originally planned schedule. Scheduled delivery of Vessel #2 is 20th June 2009.

Construction of Vessel #1 is also progressing well and is currently two weeks ahead of schedule. Scheduled delivery of Seajacks' first vessel is 20th February 2009.

Both vessels are designed, built and outfitted for North Sea operations. Seajacks has options to build five more vessels of the same design at Lamprell.