RBG Limited recently completed delivery of a fabricated structure for repairs to the BP operated Central Area Transmission System (CATS) pipeline.

Following damage to the pipeline in late June 2007, RBG was requested to provide assistance with the repairs. RBG's Fabrication division based in Invergordon, Ross-shire, was asked to manufacture a metal sleeve to strengthen and protect the affected area.

Based on engineering drawings, RBG prepared a project schedule to deliver the completed sleeve in a 20 day turnaround. Materials were procured and a core team of 20 people were involved in the sleeve fabrication.

In fact, the sleeve was fabricated, tested and delivered to the CATS terminal in Teesside and to the satisfaction of BP's project team, within a remarkable 19 days.

"We were able to turn this job around so quickly thanks to the professionalism and expertise of our team here in Invergordon," explained Ed Stainke, RBG's Fabrication Business Unit Manager. "The excellent trust and teamwork which were quickly established between the BP project team and our own people also played a key part."

Doug Sedge, RBG's Chief Executive Officer commented: "We are delighted to support BP in their efforts to return the CATS pipeline to normal operations."

Related Companies

Our Privacy Pledge

Most Popular Articles

From the Career Center
Jobs that may interest you
Assistant Operations Manager
Expertise: Marine Surveying|Operations Management|Surveying
Location: New Orleans, LA
Petroleum Inspector III
Expertise: Field Service Tech|Marine Surveying|Surveying
Location: Seattle, WA
US Fort Lupton, CO: Entry Level Operator Assistant I - III - Cementing
Expertise: Cementing
Location: Fort Lupton, CO
search for more jobs

Brent Crude Oil : $50.47/BBL 0.98%
Light Crude Oil : $49.72/BBL 1.09%
Natural Gas : $2.76/MMBtu 1.09%
Updated in last 24 hours