PCWU Topsides Sets Sail from Baku

AMEC, and its partners in the AMEC-Tekfen-Azfen (ATA) consortium, celebrated the successful completion and sail-away of the Azerbaijan International Oil Company's (AIOC) Process, Compression, Water Injection and Utilities (PCWU) topsides.

Part of the Azeri, Chirag and Gunashli field development operated by BP for the AIOC, the 12,700 tonne PCWU was completed two weeks ahead of its original schedule. It will produce oil and gas from the deepwater Gunashli field, located in 175 meters of water in the Caspian Sea, approximately 120 kilometers from the coast of Azerbaijan.

The PCWU project began in mid-2005 following the successful completion of the Compression and Water Injection topsides for the Central Azeri field.

Not only have all the schedule milestones been beaten on PCWU, but the project has also achieved an outstanding safety record, with more than 7.4 million man-hours being worked without a Day Away From Work Case.

For More Information on the Offshore Rig Fleet:
RigLogix can provide the information that you need about the offshore rig fleet, whether you need utilization and industry trends or detailed reports on future rig contracts. Subscribing to RigLogix will allow you to access dozens of prebuilt reports and build your own custom reports using hundreds of available data columns. For more information about a RigLogix subscription, visit www.riglogix.com.

Our Privacy Pledge

Most Popular Articles

From the Career Center
Jobs that may interest you
Production Engineer
Expertise: Production Engineering
Location: Houston, TX
Senior Client / Program Manager
Expertise: Geologist|Reservoir Engineering
Location: Seattle, WA
Senior Sales Representative - Oil and Gas
Expertise: Corrosion Engineering|Petroleum Engineering|Sales
Location: Harvey, LA
search for more jobs

Brent Crude Oil : $49.98/BBL 1.59%
Light Crude Oil : $49.18/BBL 1.56%
Natural Gas : $2.73/MMBtu 1.44%
Updated in last 24 hours