P-54 Cost 30% More Than Planned

Brazilian federal energy company Petrobras (NYSE: PBR) paid 30% more to build the P-54 oil platform than planned, company E&P director Guilherme Estrella told journalists in Rio de Janeiro.

Construction originally was to have cost US$650mn under the contract signed with Brazilian shipyard Mauá Jurong, but eventually rose to US$900mn.

P-54 was delivered 41 months after it was ordered, eight months longer than originally planned, Estrella said during the P-54 inauguration.

"The world of oil is not the same as it was 40 months ago. Steel prices rose and services, salaries and exchange rates have had a negative impact on prices," Estrella said.

Prices may start declining next year, Estrella said, adding construction timeframes also could get back on track.

"We propose building a platform in 37 or 38 months. The 33-month timeframe was not unfeasible but rather challenging," Estrella said.

P-54 will start producing oil in October, reaching its 180,000b/d production peak in mid-2008.

Visit BNamericas to access our real-time news reports, 10-year archive, Fact File company database, and latest research reports. Click here for a Free two week trial to our Latin America Oil & Gas information service.

Events  SUBSCRIBE TO OUR NEWSLETTER

Our Privacy Pledge
SUBSCRIBE


Most Popular Articles


From the Career Center
Jobs that may interest you
Allen Bradley PLC / HMI Programmer
Expertise: Field Comm / SCADA|Process Control|Well Control
Location: Midland, TX
 
Water Management Operator
Expertise: Rig Welder|Well Servicing & Testing
Location: Midland, TX
 
Downhole Technician I - Bakersfield, CA
Expertise: Driller|Mechanical Technician|Well Control
Location: California, CA
 
search for more jobs

Brent Crude Oil : $44.82/BBL 2.60%
Light Crude Oil : $42.53/BBL 1.61%
Natural Gas : $2.89/MMBtu 0.68%
Updated in last 24 hours