DNO Reports Yemen Progress

DNO ASA on Friday issued an update on its ongoing drilling activities in Yemen.

DNO is carrying out an extensive drilling program in Yemen in 2007 through planned drilling of 22 wells, consisting of 13 exploration wells and 9 appraisal wells.

The status of ongoing drilling operations is as follows:

Appraisal and Development Wells

Sharyoof - Block 53 (24.45%)

Sharyoof # 20, which was drilled in 2006, was originally completed as a Qishn S1C sandstone producer, but was shut down after a short while due to high water production. The well has now been re-completed and the shallower S1A sandstone interval has been brought on stream at an initial gross oil rate of 2,400 bopd. This is another successful operation adding production from the Sharyoof Field following the completion of the two recent infill wells Sharyoof # 23 and # 24, which were brought on stream in November 06 and February 07, respectively.

Drilling of Sharyoof # 26 is expected to commence shortly, and the well is planned as an infill/appraisal well at within the Sharyoof Field area.

Nabrajah - Block 43 (56.67%)

Following the interpretation of the new 3-D seismic acquired across the Nabrajah Field during second half of 2006, drilling resumed at the Field earlier this year. There are currently two drilling rigs operating at the Nabrajah Field.

Nabrajah # 14 commenced drilling on 26 April and is the second Qishn appraisal well that is based on the new 3-D seismic interpretation.

Drilling of Nabrajah # 13 commenced on 29 March and is targeting a new play concept within the Nabrajah area.

There are several additional Qishn prospects identified from the new 3-D seismic which will be drilled later this year. Contingent on the results from Nabrajah # 13, additional deeper targets may also be drilled. Following the completion of Nabrajah # 14, the plan is to fully utilize one rig in Block 43 for the remainder of the year.

Godah - Block 32 (38.95 %)

In Block 32 the joint venture group has secured an additional drilling rig for two slots back-to-back as part of the additional development drilling on the Godah field. Drilling of Godah #5 commenced on 11 April and will follow on with Godah #6 utilizing this rig. Godah #7 is planned to be drilled with another rig, and is expected to start beginning of June.

Exploration drilling

Block 44 (65.10 %)

Drilling of the Ardah #1 exploration well has been completed by DNO as Operator. The well penetrated both Qishn Formation as well as deeper targets without encountering hydrocarbons.

DNO has to date completed 4 of the 13 wells planned under the 2007 exploration program in Yemen. According to the current plan the remaining 9 exploration wells are expected to be drilled as follows:

  • Block 32: 3 wells
  • Block 43: 1 well
  • Block 44: 2 wells
  • Block 47: 1 well
  • Block 53: 2 wells

Our Privacy Pledge

Most Popular Articles

From the Career Center
Jobs that may interest you
Gas Storage Reservoir Engineer
Expertise: Petroleum Engineering
Location: Houston, TX
Well Monitoring Specialist
Expertise: WellSite Supervisor
Location: Houston, TX
Chief Mechanic (6th Gen Drillship)(Contract)
Expertise: Rig Mechanic
Location: Houma, LA
search for more jobs

Brent Crude Oil : $51.46/BBL 0.61%
Light Crude Oil : $50.52/BBL 0.64%
Natural Gas : $2.83/MMBtu 5.35%
Updated in last 24 hours