Pantheon to Run Another Liner at Padre Island Prospect

Pantheon Resources Plc on Friday issued a drilling update on its Wilson Prospect on Padre Island, Texas.

The Kindee ST 212 #1 well on the Wilson Structure was spudded on February 7, 2007. Currently, operations are being prepared to deviate around a stuck 7-inch liner at 8,500 feet (measured depth).

Pantheon said the plan is to re-drill the hole to 10,000 feet (measured depth). At this depth, it is proposed to run 7-inch liner once more. Drilling is then scheduled to resume to the planned total depth of 12,400 feet (measured depth).

During the original attempt to run the liner, the well bore collapsed. The liner became stuck when it had reached 9,300 feet. After several days of efforts to free the liner, only approximately 50% was retrieved. It was assessed that further efforts to free the remaining liner would take much longer than it would to deviate and re-drill.

Current plans envisage that after the section is re-drilled with an 8 -inch bit, it will be opened out to approximately 9 inches. The hole will then be conditioned and cleaned prior to running the liner. After the 7-inch liner is run and cemented, drilling will continue to test the primary objectives in the Upper Frio system. Similar prospects have been found to be productive elsewhere on Padre Island.

Drilling to the planned total depth is estimated to take an additional three weeks on a trouble-free basis. This includes re-drilling the lost section.

Gross best estimate potential reserves (previously described as "P50 potential reserves") for Wilson have been assessed at 9 billion cubic feet.

Pantheon's working interest in Wilson is 31.77%, subject to final documentation.


Our Privacy Pledge

Most Popular Articles

From the Career Center
Jobs that may interest you
Field Maintenance Controls Technician
Expertise: Maintenance Technician|Rig Mechanic
Location: Eighty Four, PA
Maintenance Supervisor - Drilling
Expertise: Maintenance Manager|Rig Mechanic
Location: Eighty Four, PA
Whipstock Welder
Expertise: Rig Welder|Welding|Workshop
Location: Lafayette, LA
search for more jobs

Brent Crude Oil : $51.78/BBL 0.77%
Light Crude Oil : $50.85/BBL 0.83%
Natural Gas : $2.99/MMBtu 4.77%
Updated in last 24 hours