Dodsal Completes Salalah Pipeline Project

The 680km long pipeline project from Saih Rawl in Central Oman to Salalah on the south coast of Oman has now been completed and is ready for commissioning. Dodsal & Co. LLC, the Engineering, Procurement and Construction Contractor has achieved "substantial completion" of the project ahead of schedule. Oman Gas Company and ILF & Partners, the project managers, signed the 'substantial completion certificate' on August 7, 2002. The "substantial completion certificate" was signed after completion of all testing and audit of the construction by Canadian Energy Services, who will be commissioning and operating the pipeline for Oman Gas Company.