Thule Power Expected to Leave Shipyard in Mid-May

Following various installation work at Dubai Drydocks, the reconstruction of Thule Power resumed after the rig returned to QGM Group LLC, Sharjah UAE on January 5, 2007. A complete revision of the plan to complete the rig has recently been concluded. Handover from QGM to Thule Drilling is now scheduled for mid May 2007. The rig will commence on the four year fixed contract with Saudi Aramco following mobilization to Ras Tanura, Saudi Arabia by the end of May 2007. The approximate 90 days of delay at the start of the contract from March 1st to end of May 2007 allows for a 50% dayrate deduction by Saudi Aramco from the first 90 days of operation. For Thule Drilling this penalty will have an effect on the net EBITDA contribution being reduced from US $130 million to about US $123 million over the fixed contract term.

The delay will add another US $3-4 million to the construction cost of Thule Power to about US $106 million including finance cost, supervision, administration, and extras to comply with the Saudi Aramco specific requirements to enhance the rig's capabilities. The performance bonus of US $3.6 million in favor of QGM will not be paid due to delayed completion.

Reasons for the three month delay refer to a mechanical breakdown during jacking operations at Dubai Drydocks of two of the jacking gears with long lead delivery of new spares. The default causing the breakdown has since been remedied. Also the progress made while at Dubai Drydocks was disappointing as leakage was found on all three spud cans produced by Dubai Drydocks. This caused extra docking time. At Dubai Drydocks we also experienced shortage of labor resources, limited access to cranes due to crane downtime for maintenance as well as limitations of access of QGM's and QGM's subcontractor's labor force. Consequently the improved performance expected while at Dubai Drydocks did not materialize. In addition, the preparations made by QGM prior to moving to Dubai Drydocks turned out to be inadequate. QGM's plan for meeting the completion date previously planned for mid February clearly underestimated the time and resources required after return of the rig from Dubai Drydocks.

Remedies have been implemented to secure May 2007 completion. The project management at QGM has been partly replaced and supervision strengthened also by bringing in experienced rig builders from Davie Shipyard in Canada. Sufficient workforce has been secured. The present plan is based on detailed and well documented CTRs which have been thoroughly quality checked. The plan allows for adequate time for contingency for the testing and commissioning phase.

The delayed completion has been presented to Saudi Aramco and cooperation will continue towards the adjusted commencement date with regular reporting of progress and coordination of integrated commissioning with Saudi Aramco's acceptance test procedures.

The effect of the delay in completing Thule Power will result in an increased funding requirement for Thule Drilling of about US $35 million. This requirement relates to about US $17 million for delayed commencement (including penalty) of the drilling contract, US $6 million relates to none exercise of 1.65 million warrants by founders of the Company (expire as delivery of Thule Power is completed after date of right to exercise on April 14th), and the rest to adjustment of Thule Power reconstruction cost, finance cost and other items. It is assumed that the 3.5 million warrants linked to the original bond financing will be exercised early May 2007. It is the intention of the Board of Directors to minimize dilution of values for the present shareholders by finding the optimal balance between bond and equity financing. Any equity financing will be made in favor of existing shareholders. Major shareholders have accepted to provide a subscription guarantee for the equity portion. The Board of Directors will revert with a final financing proposal.

The construction of the two 300 ft water depth jack-ups of the Friede & Goldman Super M2 design, Thule Energy and Thule Force, is progressing well at QGM and scheduled delivery is maintained as first and second quarter of 2008 respectively.

For More Information on the Offshore Rig Fleet:
RigLogix can provide the information that you need about the offshore rig fleet, whether you need utilization and industry trends or detailed reports on future rig contracts. Subscribing to RigLogix will allow you to access dozens of prebuilt reports and build your own custom reports using hundreds of available data columns. For more information about a RigLogix subscription, visit

Our Privacy Pledge

Most Popular Articles

From the Career Center
Jobs that may interest you
Shop Mechanic - Grand Prairie, TX
Expertise: Customer Service|Mechanic
Location: Grand Prairie, TX, TX
Diesel Mechanic for Williston, ND!
Expertise: Mechanic
Location: Williston, ND
Branch Manager for Heavy Equipment Dealership in Mississippi
Expertise: Facilities Management|Mechanic
Location: Mississippi, United States, MS
search for more jobs

Brent Crude Oil : $51.78/BBL 0.77%
Light Crude Oil : $50.85/BBL 0.83%
Natural Gas : $2.99/MMBtu 4.77%
Updated in last 24 hours