Transmeridian Begins Drilling Two New Wells in South Alibek Field

South Alibek Field - Kazakhstan
(Click to Enlarge)
Transmeridian Exploration has commenced drilling of two new wells in its South Alibek Field in western Kazakhstan. The ninth and tenth wells in the Field, the SA-11 and SA-12 were spudded on January 30th and February 1st, respectively. Both wells are being drilled by drilling rigs contracted from Great Wall Drilling Company, the second of which arrived in the Field in December 2005.

SA-11 is currently at a depth of approximately 3,800 feet and SA-12 is currently at a depth of approximately 4,100 feet. Both wells are programmed to reach a total depth of 12,600 feet by the end of April. The SA-11 is located approximately 1,700 feet southwest of SA-5 and SA-12 is located southwest of SA-11 and approximately 2,000 feet northwest of SA-14. The success of wells SA-11 and SA-12, both of which are located in the western flank of the proved area of the Field, should allow for continued extension of the previously estimated area containing proved reserves.

Operations Update

The Company is continuing its field operations and work-over of selected wells in spite of the extreme subzero temperatures that have affected the region's transportation, infrastructure and contractor services. The interruptions caused by these circumstances have significantly affected timing of planned works and production, and four of the seven producing wells in the Field are currently shut-in. Field production has averaged approximately 1,200 bopd since late 2005 due to weather and delays related to well workover logistics. Once scheduled work is completed and these wells are placed back on production, the Company expects production from the existing wells, including the recently drilled SA-15, to be approximately 2,500 - 3,000 bopd.

SA-15 reached its total depth of 12,600 feet in late December after 87 days of drilling. The well was perforated in mid-January, with 144 feet of perforations in the KT2 reservoirs, and is expected to be acid washed and placed on production as soon as service contractor equipment, which has been delayed by the backlog of work created by the harsh weather, is available. The Company expects to continue to improve on the timing for drilling and completion of wells as increased equipment and personnel will allow for more continuity in operations.

SA-3 was completed and placed on production on October 5, 2005 and an acid stimulation treatment was performed in late January. Results of the stimulation are considered encouraging, with 400 psi flowing tubing pressure as the well was flowed to the pit during cleaning up of the acid. Initially, the well could not be placed back on production due to a frozen flow line. The frozen flow line has been thawed and the well is now back on production and continuing to clean up.

Well SA-2 was selected as the first candidate for installation of a downhole electric submersible pump, which was installed in November 2005. After initial testing, the pump has been reset lower in the well and is back on production for further evaluation. Two additional electric submersible pumps have been purchased and are scheduled for installation in wells SA-5 and SA-17 during the next four weeks to also enhance production from these wells.

SA-1 was recently re-completed with new, more efficient tubing and the installation of new packers. The well has resumed flowing and is expected to return to a more stable flow rate as it cleans up.

The Company expects to add at least two additional drilling rigs during the first half of 2006, bringing the total rigs in operation in the Field to four. The first of the two rigs is expected to be in operation by early April, and the second rig, which is to be mobilized from China, is expected to be drilling by early June. In addition, the Company is evaluating opportunities to further accelerate development of the Field by adding a fifth and possibly a sixth drilling rig later in the year. In addition, a full-time workover rig is being sourced in order to facilitate completion operations and improve the timing and efficiency of workover activities.

Transmeridian Exploration Incorporated (TMEI) is an independent energy company established to acquire and develop oil reserves in the Caspian Sea region of the former Soviet Union. TMEI primarily targets medium-sized fields with proved or probable reserves and significant upside reserve potential. Its first major project is the South Alibek Field in Kazakhstan and it is currently pursuing additional projects in the Caspian Sea region.


Our Privacy Pledge

Most Popular Articles

From the Career Center
Jobs that may interest you
Well Monitoring Specialist
Expertise: WellSite Supervisor
Location: Houston, TX
Chief Mechanic (6th Gen Drillship)(Contract)
Expertise: Rig Mechanic
Location: Houma, LA
ET (Deepwater Drillship)
Expertise: Rig Electrician
Location: Houma, LA
search for more jobs

Brent Crude Oil : $50.79/BBL 1.30%
Light Crude Oil : $49.96/BBL 1.10%
Natural Gas : $2.77/MMBtu 2.12%
Updated in last 24 hours