Burren Energy Completes Four Development Wells on M'Boundi Field

Burren Energy PLC

Burren reports a total of 4 development wells have been completed and tested since the beginning of August, with a combined aggregate test rate of 14,800 bopd from the Vandji reservoir.

Well       M'Boundi Location                Test flow rate         Choke size
MBD 1004   Northern perimeter               4,700 bopd             48/64'
MBD 1102   North-west perimeter             2,500 bopd             40/64'
MBD 1802   South-east infill                2,600 bopd             40/64'
MBD 1901   Central infill                   5,000 bopd             48/64'


Three of these wells are on production as a result of which gross M'Boundi production is now in excess of 52,000 bopd (Burren working interest share 18,200 bopd). The fourth well, MDB 1102, is undergoing pressure build up and is expected to be placed on production imminently.