At midnight on October 11th the current operation was coring the Tiof-3 ST1 sidetrack well. Following coring, wireline logging and testing of the well will take place, as planned.

Tevét-1 Exploration well
The well was plugged and abandoned as planned and the Stena Tay moved to drill the bottom hole of the Dorade-1 well, containing the primary target.

PSC-C2, Dorade-1

The Stena Tay arrived at the Dorade-1 location on October 9th. At midnight on October 11th the current operation was preparing to re-enter the well. The well has a planned total depth of approximately 2,650m.

All reported drilling depths are referenced to the rig rotary table and all times are Universal Time (UTC) (Mauritanian time).

Wells are expected to be drilled in three production sharing contract areas during the campaign."