Mexico's Sole Platform Fabrication Project to Create Jobs
McDermott International Inc. plans to hire approximately 1,600 workers starting next month as it ramps up work on the Abkatun-A2 contract for Mexican state energy firm Petroleos Mexicanos (PEMEX).
The integrated engineering, procurement, construction and installation firm recently cut first steel on the Abkatun-A2 contract at its Altamira Fabrication yard at Altamira, Mexico. For the Abkatun-A2 project, McDermott will fabricate, install and commission the 20,000 ton platform, which includes topsides, jacket and piles. The platform will be installed in 124 feet (38 meters) of water in Mexico’s Bay of Campeche. The topsides for the project will be twice the size as those McDermott fabricated for PEMEX’s PB Litoral platform.
George Stapleton, director of fabrication operations at McDermott, told Rigzone that the company will need to hire 25 percent more workers in the fitting and welding crafts than ever before to complete the Abkatun-A2 project. The company is “very lucky” to have the project, as Abkatun-A2 is the only platform being fabricated in Mexico right now. The project, which is expected to take 18 months, will involve 1,800 man years, or 4.5 million manhours, Stapleton said. Manpower will be at its peak in April and May of next year, so McDermott will need to ramp up quickly.
At this time, McDermott estimates that the Abkatun-A2 platform will be delivered from the Altamira yard in July 2018. The company will use the Intermac 650 transportation and launch barge for the floatover of the Abkatun-A2 platform; this will mark the first time McDermott has used this vessel for a project at Altamira, Stapleton said. The Abkatun-A2 platform will provide capabilities to the existing Abkatun-Pol-Chuc, Ku-Maloob-Zaap, Cantarell and Ayatsil facilities, McDermott said in a Sept. 22 press statement. PEMEX Exploration and Production awarded the contract to McDermott in June of this year.
McDermott will invest between $13 and $14 million to upgrade the facility to accommodate the Abkatun-A2 contract. This includes upgrading the skidways at McDermott’s facility to support the deck weight of the Abkatun A2-platform. McDermott will also implement three blasting and painting enclosures to move painting from outside to inside. This will help McDermott work around some weather issues. The company also has brought some functions in-house, such as scaffolding, because, according to McDermott officials, the company can do a better job of ensuring this work complies with the company’s safety procedures.
Since work began on the fabrication yard in 2007, McDermott has invested more than $150 million in the yard, said Scott Munro, McDermott’s vice president, Americas, Europe and Africa, during a Sept. 22 media presentation in Altamira.
Part of the yard also has a free trade zone that allows the company to import materials duty free on an export project it comes in and out duty free. For project in Mexican waters, a VAT is paid when the project is delivered. Stapleton estimates this creates a project cost savings of 10 to 20 percent, making the shipyard a little more competitive for foreign work.
The fact that Abkatun-A2 – a critical platform for PEMEX – will be the heaviest deck loaded out from Altamira is the most significant challenge of the project, said Stapleton. Even with needed crane capacity in place, lifts always present a challenge for floatover projects, said Stapleton.
“We have carved up the deck in pieces based on our capacity, and the construction sequence has been designed based on our capacity,” said Stapleton.
Abkatun-A2’s tight schedule is another challenge the company faces, and it is doing all the detailed engineering for the project, Stapleton commented. To cope, the company will set up full-blown engineering office in Mexico City with 90 employees. Yard workers will also be involved in the hook-up and commissioning of the platform.
The company is committed to expanding its presence in Mexico, growing its engineering capacity in both Altamira and Mexico City, said Munro during the presentation. He added that the site at Altamira was not just chosen for its access to deepwater or quality of land, but because the local workforce is known for its welders, metallurgists and engineers, all trades which McDermott needs for success.
PEMEX Spending Cutbacks to Pull Down Regional 2017 CAPEX
Until now, PEMEX has been the principal client, but Stapleton said they hope to do more at Altamira for the export market. McDermott sees the fabrication yard primarily serving the Gulf of Mexico and West Africa. But the company has not seen much bidding activity in the Gulf recently, save for subsea module work.
“They yard was originally conceived as competing in that [deepwater] market,” said Stapleton.
However, the company would need to make some capital investments in the Altamira yard to ready it for deepwater hull work. The company could build deepwater topsides with the existing facility, Stapleton added. Currently, the Altamira yard dock has a draft of 39 feet (12 meters), which would need to be deepened for mating and tie-in.
12
View Full Article
WHAT DO YOU THINK?
Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.
- ExxonMobil Racks Up Discoveries in Guyana Block Eyed by Chevron
- Oil Market Sentiment Has Improved Significantly
- EU, US Eye Collaboration on Nuclear Materials
- EU Electricity Export to Ukraine Up 94 Percent in Two Years
- China Coal Output Falls for First Time since Government Ordered More
- USA Driving Activity to Increase to All-Time Highs
- BP Pulse Buys One of Europe's Largest Truck Stops
- UK CCUS Plans Outdated: Think Tank
- TC Energy to Sell Prince Rupert Gas Pipeline Project to First Nation
- I Squared Eyes Full Ownership of Europe Gas Storage Firm
- Norway Regulator Blasts Proposal to Halt New Oil and Gas Permits
- Chinese Mega Company Makes Major Oilfield Discovery
- EIA Drops 2024 Henry Hub Gas Price Forecast
- EIA and Standard Chartered Offer Up Latest Oil Price Predictions
- Red Sea Region Sees Another Watershed Incident
- Chevron Oil Project in Kazakhstan to Cost $48.5B
- OPEC Voices Encouragement after IEA Affirms Support for Oil Security
- Biden Govt Bares Strategy for Freight Charging, Hydrogen Fueling Infra
- Ukraine Hits Third Russian Refinery In Escalating Drone Strikes
- Rystad Looks at the Buzz Around White Hydrogen
- VIDEO: Missile Attack Kills Crew Transiting Gulf of Aden
- Norway Regulator Blasts Proposal to Halt New Oil and Gas Permits
- Chinese Mega Company Makes Major Oilfield Discovery
- What Is the Biggest Risk to Offshore Oil and Gas Personnel in 2024?
- Is Peak Oil Demand Close?
- Vessel Sinks in Red Sea After Missile Strike
- JP Morgan, Standard Chartered Reveal Latest Oil Price Forecasts
- Exxon Rights in Stabroek Do Not Apply to Hess Merger with Chevron: Hess
- Rystad Forecasts Net Production of Top Permian Producers in 2024
- Analysts Reveal Latest Oil Price Outlook Following OPEC+ Cut Extension