Tullow Delays Uganda Oilfield Sanction To Early 2017

Reuters

CAPE TOWN, Oct 27 (Reuters) - Britain's Tullow Oil plans to take a final investment decision (FID) on a new oilfield project in Uganda in early 2017, later than planned, Chief Executive Aidan Heavey told Reuters on Tuesday.

Tullow discovered oil in the East African country in 2006 and had planned to make an FID on its oilfield by the end of 2016.

"You need a pipeline route firmed down and then you need to get FID. So FID probably in early 2017 and then three years later, you would have first oil," Heavey said at the Africa Oil Week conference organised by Global Pacific & Partners.

He added Tullow expected to obtain a production licence this year in Uganda and to start oil output there in 2020.

The pipeline route to move oil from landlocked Uganda to the Indian Ocean has not yet been determined.

Uganda has been pushing for an earlier production date around 2018, citing work by other investors. But previous targets have slipped.

"If Tullow is talking of 2020, that's their business," said Ugandan Energy Ministry spokesman Bukenya-Matovu Yusuf. "CNOOC which has a production licence has been doing a lot of work toward production and our 2018 target still stands."

China's CNOOC is also investing in Uganda, alongside France's Total.

Crucial to any investment decision will be the decision on a route for an export pipeline out of the land-locked nation.

A proposed northern Kenyan route has raised security concerns as it lies near war-torn Somalia. Total has said it is considering a pipeline through Tanzania.

(Additional reporting by Elias Biryabarema in Kampala; Editing by James Macharia and Karolin Schaps)