Triple Updates on Aolong Project's Drilling in China's Heilonjiang Province

Australia's Triple Energy Ltd. provided Tuesday the following update on the drilling activities on the Company's Aolong Joint Venture project in Heilongjiang province, China.

Niaoshan-1 Well

As of 10:00 am Sept. 28 the Niaoshan-1 well had reached its programmed total depth of 4,137 feet (1,261 meters) measured depth. Upon conclusion of wireline operations a decision will be made on the next steps with regard to well completion.

Yixin-1 Well

The Yixin-1 well remains at 121 feet (37 meters) measured depth pending the arrival of necessary additional equipment as previously advised. The necessary equipment has now been mobilized to site.

WHAT DO YOU THINK?

Click on the button below to add a comment.
Post a Comment
Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

Related Companies
Events  SUBSCRIBE TO OUR NEWSLETTER

Our Privacy Pledge
SUBSCRIBE


Most Popular Articles


From the Career Center
Jobs that may interest you
Completions Supervisor
Expertise: Drilling Foreman / Drilling Supervisor|Production Engineering|Workover or Completion
Location: Watkins, CO
 
Drilling Supervisor
Expertise: Drilling Foreman / Drilling Supervisor
Location: Houston, TX
 
Tool Pusher
Expertise: Field Service Tech|Toolpusher|Well Servicing & Testing
Location: Hobbs, NM
 
search for more jobs

Brent Crude Oil : $59.02/BBL 3.79%
Light Crude Oil : $52.22/BBL 3.07%
Natural Gas : $2.92/MMBtu 1.31%
Updated in last 24 hours