Inpex Launches Hull of FPSO for Ichthys LNG Project's in DSME's Okpo Yard

Inpex Corporation (Inpex) reported Monday that it has launched the hull of the floating production, storage and offloading (FPSO) facility for the Inpex-operated Ichthys liquefied natural gas (LNG) Project from the dry dock at the Daewoo Shipbuilding and Marine Engineering (DSME) shipyard in Okpo, South Korea.

The launch on Sunday, July 6, saw the 1,102 foot- (336 meter-) long hull – equivalent to more than 3 soccer fields in length – floated out of the dry dock and positioned quayside where construction will continue.

Ichthys LNG Project offshore Director Claude Cahuzac said the milestone was an impressive achievement, with an enormous amount of work carried out since the FPSO’s keel laying ceremony.

“Pre-fabricated blocks weighing around 60,000 tons in total have been lifted into the dry dock and assembled to create the full-size FPSO hull we see on the water today,” Cahuzac said.

“While the hull is now at its full length from stern to bow and floating, it does not mean the FPSO is complete. We still have some work to do to complete the hull, and even more for the entire FPSO, including the fabrication and integration of the topsides, living quarters and our next major milestone – the installation of the turret, which is currently under construction in Singapore.”

The FPSO will be moored about 2.17 miles (3.5 kilometers) from the Ichthys LNG Project’s Central Processing Facility (CPF). It will process and store condensate from the CPF and periodically offload stabilized condensate to shuttle carriers for export directly to market.

The 1,102 foot by 193.5 foot (336 meter by 59 meter) FPSO is designed to hold more than one million barrels of condensate and will have the capacity to accommodate a workforce of up to 200 people.

Once complete, the facility will be towed 3,479.6 miles (5,600 kilometers) to the Ichthys Field in the Browse Basin, offshore Western Australia, where it will be permanently moored to the seabed for the life of the Project.

The Ichthys LNG Project recently celebrated its most significant construction milestone to date after officially marking 50 percent completion June 25.


Click on the button below to add a comment.
Post a Comment
Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

Related Companies

Our Privacy Pledge

Most Popular Articles

From the Career Center
Jobs that may interest you
Diesel Mechanic for Williston, ND!
Expertise: Mechanic
Location: Williston, ND
Branch Manager for Heavy Equipment Dealership in Mississippi
Expertise: Facilities Management|Mechanic
Location: Mississippi, United States, MS
Sr Machine Maintenance Technician
Expertise: Machinist
Location: Godley, TX
search for more jobs

Brent Crude Oil : $51.78/BBL 0.77%
Light Crude Oil : $50.85/BBL 0.83%
Natural Gas : $2.99/MMBtu 4.77%
Updated in last 24 hours