Premier Oil Updates on Indonesia, Vietnam Projects



Premier Oil provided an update on its development projects in Indonesia and Vietnam recenty.

At the Premier-operated Anoa Phase 4 project in the Natuna Sea Block A, off Indonesia, installation of the final platform commenced June 8 and is expected to be fully commissioned by September, with first gas flowing earlier in late July.

"The (Anoa Phase 4) project will commercialize around 200 billion cubic feet of undeveloped proven reserves in the Anoa field on Natuna Sea Block A," Premier said in a press release which gave an update on its operations.

Premier's other development projects in Southeast Asia are expected to come into production in 2014. Pipelay work for the Pelikan and Naga project in Indonesia was completed in June and the wellhead platforms are expected to be installed in the third quarter of the year.

On the Dua project, which is being developed as a three-well subsea tie back to the Chim Sao field in the Nam Con Son Basin off Vietnam, development drilling will commence in the fourth quarter with two of the development wells expected to be completed by year end.



WHAT DO YOU THINK?


Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

RELATED COMPANIES
For More Information on the Offshore Rig Fleet:
RigLogix can provide the information that you need about the offshore rig fleet, whether you need utilization and industry trends or detailed reports on future rig contracts. Subscribing to RigLogix will allow you to access dozens of prebuilt reports and build your own custom reports using hundreds of available data columns. For more information about a RigLogix subscription, visit www.riglogix.com.