Skarv FPSO's Stay Extended at Kvaerner Stord Yard

The Skarv FPSO stay at Kvaerner Stord yard has been extended to mid July 2011.

This is due to more work than anticipated with the pressure testing of the process plant, completion and hand over of equipment and systems. This work is best completed while the vessel is at the yard.

Our priority is safe, compliant and efficient start up of production which is now deferred from 3Q to 4Q 2011. In the period between tow out and start up the vessel will be installed and connected to the subsea infrastructure including pull in of risers, completion of commissioning and full system integration tests and start up preparations.

Events  SUBSCRIBE TO OUR NEWSLETTER

Our Privacy Pledge
SUBSCRIBE


Most Popular Articles


From the Career Center
Jobs that may interest you
Lead I&E Technician
Expertise: Instrumentation Technician
Location: Lafayette, LA
 
Lead Mechanic
Expertise: Mechanic
Location: Lafayette, LA
 
Mechanical Design Support Engineer
Expertise: Design Engineer
Location: Anchorage, AK
 
search for more jobs

Brent Crude Oil : $48.06/BBL 2.51%
Light Crude Oil : $45.77/BBL 2.17%
Natural Gas : $2.97/MMBtu 2.30%
Updated in last 24 hours