StatoilHydro has been granted consent to use the Aker Spitsbergen semisub to plugback a well on the Asgard field. The purpose of the operations is to permanently plug exploration well 6506/12-8 (Smorbukk Sor).

StatoilHydro has a five-year contract period with Aker Spitsbergen. The operation is scheduled with a budgeted duration of 26 days for the plugging of Smorbukk. Start-up will be in September 2009.

Aker Spitsbergen is a semisubmersible drilling rig of Aker H-6e type, and is currently (along with Aker Barents) the world's largest drilling facility. The hull was built in Dubai, while completion and outfitting of the deck was carried out at the Aker Solutions' yard on Stord.
 

Printer Friendly Version
Email this Page
Events  SUBSCRIBE TO OUR NEWSLETTER

Our Privacy Pledge
SUBSCRIBE


Most Popular Articles


From the Career Center
Jobs that may interest you
Senior Reservoir Engineer
Expertise: Petroleum Engineering|Reservoir Engineering
Location: Houston, TX
 
Rentals & Asset Manager - Surface & Frac
Expertise: Asset Management|Operations Management|Subsea Engineering|Technical Sales
Location: Houston, 
 
Territory Sales Manager - Subsea Wellheads
Expertise: Sales & Marketing|Subsea Engineering|Technical Sales
Location: Houston, 
 
search for more jobs

Brent Crude Oil : $66.54/BBL 2.32%
Light Crude Oil : $60.72/BBL 2.95%
Natural Gas : $2.95/MMBtu 1.02%
Updated in last 24 hours